Refurbishment of the Victoria Falls International Airport domestic terminal is expected to be completed at the end of this month.
According to Civil Aviation Authority of Zimbabwe Public Relations Manager, Annajulia Hungwe, the terminal is now 70% complete. It had been closed for refurbishments as part of the airport project, with domestic flights being operated from the international terminal.
Hungwe said although the terminal would be completed this month, air-conditioning will only be fully installed by the end of October.
“Work on the airport is progressing well and the whole project is now 95% complete,” she said adding that development was on schedule.
Source: tourismupdate.co.za